CONSTRUCTION

Construction Engineering of the Kaliningrad LNG Regasification Terminal

Project: Construction of the terminal on reception, storage and regasification of the liquefied natural gas (LNG) in the Kaliningrad region Jetty under the protection of a breakwater. Installation of trunk line to shore with all services.
Location: Kaliningrad
Construction period: 2017
Description: Installation of large-diameter steel caissons and insertion segments. Installation analysis of all heavy lifts with offshore supervision.

BREAKWATER
Large-diameter steel caissons and insertion segments 29 pieces
Width: 26 m
Length: 600 m

JETTY
Piles Ø 1220×16 mm
L = 35-45 m, m = 20-25 t
159 pieces
Width: 40 m
Length: 100 m